CRCF requirements
This page lists all the additional requirements mentioned in the methodology, that apply for projects seeking certification under the European Commission's CRCF.
Project Developers shall also follow all requirements in the Rainbow Procedures Manual on CRCF.
Eligibility and scope
🇪🇺CRCF requirement: Confirmation of the origin of the CO2 stream
If the facility at which the CRCF-project captures CO2 is not subject to monitoring of the biogenic CO2 amount under the EU Emission Trading System (EU-ETS), Project Developers shall provide access, immediately at request, to representatives of the VVB, Rainbow or relevant national authorities to allow unannounced C14 testing of the CO2 stream leaving the facility, and if relevant, prior to being mixed with any separately captured fossil CO2 stream. If the biogenic origin cannot be confirmed, then no credits shall be issued for the corresponding monitoring period.
🇪🇺 CRCF requirement: Eligible storage
For CRCF-projects, the capture facility shall be located in the European Union and the storage site(s) shall be permitted under the Directive (EU) 2009/31/EC on the geological storage of carbon dioxide.
Principles & requirements
🇪🇺 CRCF requirement: Biomass sustainability
In addition to meeting all requirements outlined above, Projects seeking certification under the CRCF shall also comply with the following:
RED-certified biomass
Project shall use biomass that is compliant with the EU's Renewable Energy Directive (RED) III. Specifically, this means that
biomass shall be compliant with the sustainability requirements set out in Article 29 of the RED for the purposes referred to in Article 29, Paragraph 1 (a), (b) and (c), even if the project does not generate renewable energy that is taken into account under the RED.
the requirements on GHG savings set out in Article 29, Paragraph 10 shall only be met if the CO2 is captured at a facility producing heat, electricity or a biofuel, bioliquid or biogas. The GHG savings criteria apply to the product of the facility.
biomass from waste or residues from agricultural, aquaculture, fisheries and forestry residues are subject to the sustainability requirements set out in Article 29, Paragraphs 2 to 7. Other biomass types are not subject to the requirements in these paragraphs.
Compliance shall be demonstrated by certification of the biomass from
voluntary schemes approved by the Commission in accordance with Article 30, Paragraph 4 of RED, or
national schemes recognized by the Commission in accordance with Article 30, Paragraph 6 of RED, or
schemes recognized by the competent national authority in the state where the BioCCS capture facility is located.
Additional biomass sustainability requirements
Project Developers shall also demonstrate that
biomass is not identified as being produced from a high indirect land use change risk feedstock, as defined in the Delegated Regulation 2019/807 to the RED.
if biomass is sourced from areas designated by the national competent authority for
conservation, including areas covered by the national restoration plan established under
Regulation (EU) 2024/1991, or in habitats that are protected, the sourcing shall be in
accordance with the conservation and restoration objectives for those areas.
CO2 captured from energy production covered under RED
If CO2 is captured from an energy production process covered by the RED, Project Developers shall demonstrate that
the national implementation of that directive applies to the operator of the energy production process and that the operator complies with this national implementation.
the operator complies with any measures in that national implementation that ensure that woody biomass is used according to the list of priorities established in Article 3, Paragraph 3 of the RED, including any derogations introduced by Member States under Article 3, Paragraph 3 (a), if the operator benefits from a relevant support scheme for energy production.
the operator does not receive direct financial support from Member States for the use of saw logs, veneer logs, industrial grade roundwood, stumps and roots to produce energy, in line with Article 3, Paragraph 3 (c)
Facilities regulated under the RED undergo periodic assessment of compliance with the sustainability requirements by Member State competent authorities. This periodic assessment shall not prevent the compliance assessment conducted by the VVB for approval of credit issuance. In practice, this means that the VVB does not need to wait for the completion of an ongoing RED assessment of compliance before assessing the BioCCS project and approving credit issuance. However, if the Member State assessment results in any non-conformity with Article 29 of the RED, Project Developers shall notify Rainbow and the VVB immediately.
Voluntary compensation of biomass
To support the regeneration of natural carbon stocks used for the generation of permanent carbon removals, Project Developers may purchase carbon farming sequestration units and report the amount in the monitoring report.
🇪🇺 CRCF requirement: Risk assessment
Project Developers seeking compliance with the EU's CRCF shall additionally evaluate and address the following risks.
Climate change adaptation
To comply with the do-no-significant-harm to climate change adaptation criteria, Project Developers shall identify the physical climate risks that are material to the project from those listed in Section II of Appendix A to Annex 1 of the Commission Delegated Regulation (EU) 2021/2139 and perform a robust climate risk and vulnerability assessment following the steps outlined in Section I of that same appendix.
Sustainable use and protection of water and marine resources
Any potential risks due to the project to the good status or the good ecological potential of bodies of water, including surface water and groundwater, or to the good environmental status of marine waters. In the case that pollutants that are scrubbed from flue gases in order to reduce air pollution may be released to a body of water, the air pollution benefit and the availability of alternative discharge strategies shall be taken into consideration when evaluating the impact on water quality.
Addressing the following Minimum environmental and social risks defined in the Rainbow Standard Rules is equivalent to addressing this risk:
Minimize pollutant discharges to water, noise and vibration
Avoid and/or minimize negative impacts on terrestrial and marine biodiversity and ecosystems
Minimize water consumption and stress in the project
Circular economy, efficient use of sustainably sourced bio-based materials
Any potential risks to the circular economy objectives from the projects, considering
the project leads to significant inefficiencies in the use of materials or in the direct or indirect use of natural resources such as non-renewable energy sources, raw materials, water and land at one or more stages of the life cycle of products, including in terms of durability, reparability, upgradability, reusability or recyclability of products
the project leads to a significant increase in the generation, incineration or disposal of waste, with the exception of the incineration of non-recyclable hazardous waste
the long-term disposal of waste may cause significant and long-term harm to the environment
Pollution prevention and control
Any potential risks to generate a significant increase in the emissions of pollutants to air, water or land from the project. Where facilities are within the scope of Directive 2010/75/EU they shall comply with all requirements arising from that Directive.
Where facilities are not in the scope of that Directive, addressing the following Minimum environmental and social risks defined in the Rainbow Standard Rules is equivalent to addressing this risk.
Minimize pollutant emissions to air
Minimize pollutant discharges to water, noise and vibration
Minimize generation of waste and release of hazardous materials, chemical pesticides and fertilizers
Protection and restoration of biodiversity and ecosystems
Any potential risks from the project to the good condition or resilience of ecosystems or to the conservation status of habitats and species, including those of Union interest or to the achievement of targets or obligations set out in national restoration plans established under Regulation (EU) 2024/1991.
Addressing the following Minimum environmental and social risks defined in the Rainbow Standard Rules is equivalent to addressing this risk. Note that any potential risk to targets or obligations in national restoration plans shall be addressed separately.
Avoid and/or minimize negative impacts on terrestrial and marine biodiversity and ecosystems
Protect the habitats of rare, threatened, and endangered species, including areas needed for habitat connectivity
Do not convert natural forests, grasslands, wetlands, or high conservation value habitats
Minimize soil degradation and soil erosion
Minimize water consumption and stress in the project
GHG Quantification
🇪🇺 CRCF requirement: Data sources
In addition to the data listed in the table above, Project Developers of CRCF-projects shall additionally monitor and update the fraction of injected CO2 dedicated for carbon removals under the CRCF, FCRCF.
🇪🇺 CRCF requirement: Recognition under different schemes
Project Developers can choose to credit part of net carbon removal under a scheme other than the CRCF. In this case, the fraction credited under the CRCF, FCRCF shall be applied to the net removal calculation in Eq. 1 .
🇪🇺 CRCF requirement: Emission factors biomass production
For CRCF-compliant projects, Project Developers shall follow the hierarchical list below for selecting biomass production emission factors:
RED III disaggregated default values for term eec,
Default values at regional level (NUTS2),
Calculate averages based on local farming practices based on e.g. data of a group of farms, as an alternative to using a single actual value
Note that the use of representative emissions factors from other databases or literature is not allowed under the CRCF.
🇪🇺 CRCF requirement: Discount factor
For CRCF-projects, the discount factor is applied to the gross GHG removals, Rproject.
🇪🇺 CRCF requirement: Parasitic load approach
Project Developers seeking certification under the EU CRCF shall only use the full approach (biomass-based calculation) to determine emissions from parasitic load demand.
Sampling and measurements
🇪🇺 CRCF requirement: Measurements of CO2 stream
In addition to following the requirements set out in this section, CRCF projects shall ensure measurements of the CO2 stream are taken in accordance with Articles 40-46 and Article 49 of the European Commission's Implementing Regulation 2018/2066.
Last updated