GHG quantification
General GHG quantification rules can be found in the Rainbow Standard Rules.
Calculations of GHG emissions for the baseline and project scenarios shall follow a robust, recognized method and good practice guidance. The overall methodological approach is a comparative life cycle assessment (LCA) at the project-scale, based on ISO 14064-2:2019.
Mineralization projects certified under this methodology may be eligible for removal and avoidance Rainbow Carbon Credits.
Avoidance RCCs from fossil or calcination CO2 storage are calculated using the same approach as for removals from biogenic and atmospheric CO2, and are simply assigned a different credit type (avoidance instead of removal).
Avoidance RCCs from reduced cement use are calculated and issued according to a separate accounting mechanism, described below. This conservative approach results in double counting the project's induced emissions, and avoids the need for allocation of emissions/removals.
GHG quantification shall be completed for each reporting period. The duration of the reporting period is chosen by the Project Developer and may be either each mineralization batch, each calendar year, another duration shorter than 1 year, or a maximum of 18 months.
This methodology shall be used in conjunction with the following Rainbow modules:
Functional unit
Two different functional units are used:
1 tonne of mineralized material produced (e.g. 1 tonne of carbonated concrete, 1 tonne of carbonated aggregate...)
1 tonne of captured CO2
Credits are issued on the basis of mineralized material production, so this may be considered the main functional unit. Captured CO2 is used as a secondary functional unit for comparability across CDR technologies.
System boundary
The project system boundary shall include only the activities that are additional to the business as usual (BAU) scenario.
The baseline scenario system boundary shall include the processes that would have occurred in the absence of the project.
For example,
if the project performs direct carbonation of fresh concrete during hydration, the project boundary shall not include the upstream emissions from cement production.
if the project captures biogenic CO2 flue gas from an anaerobic digestion site, the project boundary shall not include the emissions from anaerobic digestion, or the embodied emissions from the digester, because these would have occurred anyway. The project boundary shall include the embodied emissions from the CO2 capture machinery added to the digester, because this was installed and used specifically for the purpose of carbon capture.
if the project uses a portion of a concrete facility's flue gas (diverting the CO2 stream, using part for mineralization , and returning the unused portion to the main flue gas stream to be emitted), the project boundary shall not include the emission of unused CO2 that returns to the flue gas stream.
A summary of the calculation approach is presented below, and detailed descriptions and equations for calculating GHGs are in the respective Project and Baseline scenario sections.
For removals and avoidance from mineralization:
The project system boundary shall include at least the following elements where relevant and additional (i.e. beyond BAU):
production of any non-waste inputs and additives
transport of inputs to the project site (e.g. CO2, recycled concrete, alkaline feedstock...)
onsite energy use (electricity, fuels, heat...) related to e.g. preparation of feedstock, and the mineralization process
fugitive CO2 leaks during CO2 transport
carbon storage
see Figure 1 below for the system boundary diagram.
The baseline system boundary shall include:
any removals that would have occurred naturally from mineralization of the alkaline feedstock, and/or
any use-phase carbonation benefits that would have naturally occurred at greater rates had the project not altered the material or process.
Removals and avoidance from mineralization are calculated using the following high-level equations, detailed in their respective sections below.
Calculations: Removals and avoidance from mineralization
(Eq.1) Snet=ΣSproject−ΣSbaseline−ΣEproject
where,
Snet represents the net carbon storage from the project during the reporting period, in tonnes of CO2eq. This storage may be counted as removals or avoidance, depending on the type of CO2 stored, as calculated in Eq. 2 and 3.
Sproject represents the project's gross GHG storage from mineralization, in tonnes of CO2eq, calculated in Eq. 15 or 19.
Sbaseline represents any baseline GHG removals from mineralization of alkaline minerals in their alternative use, representing permanent storage that would have occurred anyway in the absence of the project, in tonnes of CO2eq, calculated in Eq. 7.
Eproject represents the project's induced GHG emissions, in tonnes of CO2eq, calculated in Eq. 8.
(Eq.2) Removal RCCs=Snet∗Fbio, atm
Where,
Removal RCCs represents the amount of removal Rainbow Carbon Credits to be issued during the reporting period, from carbon storage from mineralization.
Snet was calculated in Eq. 1.
Fbio, atm represents the fraction of CO2 that is biogenic or atmospheric, as described in the Allocation of captured carbon: removals vs. avoidance section
(Eq.3) Avoidance RCCs=Snet∗(1−Fbio, atm)
Where,
Avoidance RCCs represents the amount of avoidance Rainbow Carbon Credits to be issued during the reporting period, from carbon storage from mineralization.
Snet was calculated in Eq. 1.
Fbio, atm represents the fraction of CO2 that is biogenic or atmospheric.
For avoided GHGs from reduced cement:
The project system boundary shall include emissions from the manufacture of the actual quantity of cement used in the concrete mix designs, in which the carbonated materials are used.
The baseline system boundary shall include emissions from the manufacture of the quantity of cement that would have been required to achieve the same functional performance using conventional materials or methods, for the given concrete mix design. This will likely represent a larger amount of cement than in the project scenario, since mineralization projects may enhance binder strength and reduce the total cement required.
Avoided GHGs from reduced cement are calculated using the equation below.
These calculations do not account for carbon storage, and do not allow for allocation of induced emissions between the mineralization removal and the avoidance/reduced product.
Calculations - Avoidance from reduced cement
(Eq.4) Eproject, cement=Eproject+(Acement, project∗EFcement)
where,
Eproject, cement represents the total project scenario emissions from manufacturing and using cement for the reporting period, in tonnes of CO2eq. It is composed of normal cement manufacturing emissions, upstream of the project activity and which were excluded from the Storage calculations, plus the additional induced emissions due to the project mineralization activity.
Eproject represents the induced GHG emissions from the project during the verification period, in tonnes of CO2eq, calculated in Eq. 8.
Acement, project represents the amount of cement used by the project in the reporting period, in tonnes of cement.
EFcement represents the emission factor for cement, in tonnes of CO2eq per tonne of cement. Possible sources for this emission factor are described in the Baseline scenario section.
(Eq.5) Ebaseline,cement=Acement,baseline∗EFcement
where,
Ebaseline, cement represents the baseline scenario emissions from manufacturing and using a functionally equivalent amount of cement for the reporting period, in tonnes of CO2eq.
Acement, baseline represents the amount of cement needed in the baseline scenario to fulfill the same function as the project-manufactured cement. This is expected to be higher than the amount needed in the project scenario, thanks to the project's improvements.
EFcement represents the emission factor for cement, as described in Eq. 4. The same emission factor shall be used for the project and baseline scenario.
(Eq.6) Eavoided=Ebaseline, cement−Eproject, cement
where,
Eavoided represents the avoided GHG emissions from the project scenario, in tonnes of CO2eq.
Ebaseline, cement was calculated in Equation 5.
Eproject, cement was calculated in Equation 4.
Allocation
Allocation of captured carbon: removals vs. avoidance
Credits can be issued from mineralization processes that result in both
CDR/removals, from using biogenic and atmospheric (e.g. DAC) CO2, and
CCS/avoidance, from using fossil and calcination CO2.
The same calculation method applies to all CO2 sources, they are simply assigned different credit types upon issuance (i.e. removal vs avoidance, see Eq. 2 and 3).
If the CO2 stream used in the mineralization batch is 100% biogenic/atmospheric or 100% fossil/calcination, no allocation is needed. All carbon storage and project induced emissions are fully attributed to removal or avoidance, respectively.
If the CO2 stream is mixed, Project Developers must determine the proportion of biogenic/atmospheric vs. fossil/calcination carbon, according to Article 39 of the EU ETS monitoring and reporting (even for non-EU based projects), summarized here for informative purposes only:
conservatively assume all CO2 is fossil/calcination CO2, or
use mass balance of material inputs by type, or
use measurement method, e.g. C14 testing, or
use other standards and analytical methods, subject to approval by Rainbow and the VVB.
The proportion of CO2 types shall be used to allocate the following, which are accounted for in Eq. 2 and 3:
Carbon storage: CO2 flows shall assume a proportional repartition of the two CO2 types in the different CO2 fates (e.g. successfully carbonated CO2, inflow and outflow CO2, unsuccessfully carbonated CO2 left in pore space...).
Induced emissions: project emissions shall be proportionally assigned to removal or avoidance based on the share of CO2 input from each source.
For example, if a project:
has a mixed CO2 stream of 50% fossil CO2 and 50% biogenic CO2
measures total gross carbon storage of 100 tCO2eq
calculates project induced emissions of 10 tCO2eq, plus 1 tonne of fugitive CO2 leaked from transport
Gross carbon storage repartitioned proportionally:
50 tCO2eq from fossil CO2
50 tCO2eq from biogenic CO2
Project induced emissions repartitioned proportionally:
5 tCO2eq from fossil CO2
5 tCO2eq from biogenic CO2
Fugitive CO2 leaked from transport, repartitioned proportionally:
0.5 tonnes fossil CO2 leaked, counted as 0.5 tCO2eq (fossil CO2 has a GWP of 1)
0.5 tonnes biogenic CO2 leaked, counted as 0 tCO2eq (biogenic CO2 has a GWP of 0)
This would result in
Avoidance credits from fossil CO2 mineralization = 50−5−0.5=44.5 tCO2eq
Removal credits from biogenic CO2 mineralization = 50−5−0=45.0 tCO2eq
Allocation between existing activities and baseline activities
When a process is shared between the project scope and BAU activities (e.g. total electricity use at a site performing both cement manufacturing and mineralization), only the portion attributable to the project and additional to the baseline should be included. This allocation should follow one of the approaches below:
Subdivide the system and isolate measurements to collect only input/output data directly relevant for the project scope (e.g. install electricity meters at the entry point of the mineralization process).
If subdivision is not feasible, allocate shared processes based on a relevant underlying characteristic of the shared systems (e.g. by mass for jointly transported materials, by economic value for co-products with distinct markets...).
This allocation shall be applied at the data collection stage. Project Developers shall do this allocation outside of the GHG quantification equations, and submit allocated data into the removal and avoidance calculations (with justification/proof of work for allocation).
Assumptions
By default, future uses (beyond the product's first life) or end-of-life treatment of the carbonated material will not lead to reversals. This assumes no significant changes in environmental conditions (e.g. pH or fire exposure) that would cause CO2 release.
A standard transport distance of 50 km is assumed for final product (concrete and/or carbonated solid materials) delivery. Transport emissions for distances below this threshold are considered equivalent between the baseline and project scenarios, and can be excluded from the project system boundary. Transport emissions for distances above this threshold shall be included in project induced emissions calculations.
For directly carbonated cement (e.g. during curing or hydration/mixing), it is assumed that either no significant amount of unreacted CO2 remains trapped in the pore space, or that any trapped CO2 will eventually react fully with the cement matrix.
All carbonated material from the same mineralization batch has similar characteristics.
Baseline scenario
The baseline scenario is twofold, and is detailed in following sections:
Removals from mineralization that would have occurred anyway, from alternative feedstock use/management (for mineralization of solid materials such as SCMs and aggregates) and in use-stage concrete carbonation (for all technology types).
Avoidance from reduced cement shall be considered for projects issuing avoidance credits from reduced cement use, thanks to improved binder strength.
The baseline scenario structure remains valid for the entire crediting period but may be significantly revised earlier if:
The Project Developer notifies Rainbow of a substantial change in project operations or baseline conditions, and/or
The methodology is revised, affecting the baseline scenario.
The specific values within the baseline scenario will be updated during each crediting period, using project data to accurately reflect the equivalent of the project’s operations.
Baseline CO2 storage
The baseline scenario shall account for natural mineralization from both:
the alternate fate of non-cement alkaline feedstock, and
the use-phase natural mineralization of cement-based feedstock, that would have occurred anyway.
For alkaline feedstocks other than cement, Project Developers shall assess the natural mineralization of the feedstock upon exposure to atmospheric CO2, if it hadn't been used by the project for accelerated carbonation. The extent of natural carbonation depends on the:
alternative fate of alkaline feedstock
type and duration of exposure to CO2
mineralogy
particle size
Project Developers shall either:
estimate baseline removals in alkaline feedstock using a description and proof of common practices for managing the alkaline material, mineralization models, scientific literature, or internal experiments, or
only if the feedstock is recycled concrete aggregate, opt for a default assumed carbon removal rate in the baseline scenario of 6.67 kgCO2eq/m3 of recycled concrete, in loose aggregate form.
For direct use of cement as a feedstock (e.g. carbonation curing), some natural mineralization of feedstock occurs during its use-phase in concrete. If the project technology only accelerates the rate of this carbonation, rather than causing additional net carbonation gains, then the portion of mineralization that would have occurred anyway (albeit at a slower pace) shall not be credited. Project Developers shall demonstrate that the CO2 mineralized by the project would not have occurred naturally without the project intervention. This may be justified by:
The fundamental design or operating principles of the technology, or
Selecting an appropriate post-treatment measurement time that excludes mineralization likely to occur during early use-phase conditions, or
Modeling the expected BAU mineralization, using recognized datasets or modeling tools, or
Opting for a default assumed carbon removal rate in the baseline scenario of 125 kgCO2eq/tonne of carbonated cement.
Any natural carbon unaccounted for, that would have occurred without the intervention, shall be counted as baseline removals.
If a first screening assessment based on conservative estimates demonstrates combined baseline removals (sum of alkaline feedstock and concrete use phase) are <1% of the net project removals, then baseline removals may be set to 1%, and the Project Developer does not need to collect more precise baseline removal information. Otherwise, the Project Developer may choose to collect/model baseline removals in detail in order to prove and apply a lower baseline removal rate.
Calculations: Baseline CO2 stored
(Eq.7) Sbaseline=Smineralizationfeedstock+Suse phase carbonation
Where
Sbaseline was described in Eq 1
Smineralization feedstock represents baseline carbon storage from natural mineralization of alkaline feedstock, corresponding to the amount of feedstock used by the project in the reporting period, in tCO2eq.
Suse phase carbonation represents baseline removals from mineralization of cement during the concrete use-phase that are larger than the use-phase carbonation for the project material, corresponding to the amount of concrete or cement produced by the project in the reporting period, in tCO2eq.
Baseline induced emissions
Baseline induced emissions are only considered for avoidance credits from avoided cement production. In this case, baseline induced emissions shall include the emissions from producing an equivalent amount of cement to serve the same purpose (compressive strength, lifetime...) as the cement produced in the project scenario.
Emissions are calculated based on the quantity and emission intensity of cement used in the project scenario compared to the baseline. While the emission factor of cement production remains the same (since mineralization projects typically do not alter upstream or downstream cement/concrete production), the total amount of cement needed in the concrete design mix may differ. This is because the project may create a stronger binder, requiring less cement than conventional practices.
To determine the quantity of cement avoided, Project Developers shall provide the cement usage ratio between the project and baseline scenarios for each end use of the carbonated material.
This shall be proven using the stated concrete mix designs used by the client using the carbonated material, demonstrating a lower cement use than otherwise used, or similar project-specific estimates (i.e. not default global replacement rates).
Cement emission factors shall be taken from the following sources, in decreasing order of preference:
project-specific sources, provided by the client using the carbonated material (e.g. EPDs), or
low-carbon cement thresholds (e.g. provided by the Global Cement and Concrete Association Low Carbon Rating)
the Ecoinvent database, presented in Appendix 1, with a 20% deduction applied for conservativeness.
Other sources of emission factors may be submitted by the Project Developer, and approved by the Rainbow Certification Team and the VVB. Any emission factor must meet the data requirements outlined in the Rainbow Standard Rules, and come from traceable, transparent, unbiased, and reputable sources. A conservative uncertainty deduction shall be applied if the value is not project-specific.
Calculations from this life cycle stage are presented above in Eq. 4-6 in the system boundary section above.
Project scenario
An example of a typical project design and system boundary is shown in Figure 1. Each life cycle stage is detailed in the following sections.

Calculations: Total project induced emissions
(Eq. 8) Eproject=ECO2 capture+Efeedstock+Emineralization
Where,
Eproject was described in Eq. 1.
ECO2 capture is calculated in Eq. 9.
Efeedstock is calculated in Eq. 13.
Emineralization is calculated in Eq. 14.
Project CO2 capture
This stage includes process emissions from the CO2 capture facility, CO2 transport emissions, and CO2 leakage during transport.
Induced emissions from the CO2 capture process shall only include emissions/activities that would not have occurred in the baseline.
Typically, CO2 capture is done on industrial sites that are already operating and emitting CO2. In this case, emissions from the industrial site operations and embodied emissions shall not be counted towards the CO2 capture. Furthermore, the CO2 itself is considered a waste product, and according to the waste cutoff LCA principle, is modeled as entering the project system boundary with no environmental burden/emissions.
Processes that may be considered in this stage may include but are not limited to:
additional infrastructure/machinery/instruments that are required for carbon capture (note that only substantial pieces that contribute to at least 1% of the total project life cycle emissions should be included, according to the Riverse Standard Rules. This can be assessed with a screening LCA using estimates, and if deemed substantial, more precise data shall be provided).
additional energy use required for carbon capture: Project Developers shall isolate the amount of energy used at the site that is only for carbon capture, that is not related to the site's BAU activities.
energy or material use from purification and processing of CO2 streams, for example through chemical (e.g. amine-based absorption) or physical treatment (cryogenic separation or membrane separation).
For infrastructure calculations and emission factors, see the Infrastructure and machinery module. For energy use calculations and emission factors, see the Processing and energy use module.
Induced emissions from the transport of CO2 to the mineralization site shall be included. This may include transport via truck, pipeline, ship, or other methods.
For transport calculations and emission factors, see the Transportation module.
The following three methods are recommended for measuring and reporting CO2 leakage during transport, but other methods suggested by the Project Developer may be considered on a case by case basis:
Difference in CO2 shipped/received: Project Developers record the amount of CO2 leaving the capture site, and the amount entering the mineralization process. Any difference is assumed to be CO2 leaked during transport, and counted as project induced emissions.
Literature-based leakage rates: Project Developers may propose conservative leakage rates from scientific literature, if they are well documented, from reputable sources, and are representative of the project-specific technology.
Justification that leakage is negligible, under at least one of the following conditions:
it is 100% biogenic and/or atmospheric CO2, or
it came from a flue gas stream, where the unused flue gas is emitted anyway, or
transport technologies are proven to have negligible CO2 leakage (e.g. pressurized insulated containers)
Calculations: Project CO2 capture
(Eq. 9) ECO2 capture=ECO2 capture process+ECO2 capture infra+ECO2 transport+ECO2 transport leakage
Where
ECO2 capture represents the total project emissions from the CO2 capture life cycle stage, in tCO2eq.
ECO2 capture process represents the emissions from any additional energy or consumable materials used in the CO2 capture process, calculated using the Processing and energy use module, in tCO2eq.
ECO2 capture infra represents the emissions from any additional infrastructure or machinery used for CO2 capture, calculated using the Infrastructure and machinery module, in tCO2eq.
ECO2 transport represents the emissions from transporting CO2 to the mineralization site, calculated using the Transportation module, in tCO2eq.
ECO2 transport leakage represents the emissions from fugitive CO2 leaked during CO2 transport, in tCO2eq. It may be calculated using Eq 10, 11, 12, or a different approach.
(Eq. 10) ECO2 transport leakage=PurchasedCO2−InflowCO2
Where,
ECO2 transport leakage was described in Eq. 9.
PurchasedCO2 represents the total mass of CO2 leaving the CO2 supplier and destined for the mineralization site, throughout the reporting period, in tCO2eq.
InflowCO2 represents the mass of gaseous CO2 entering the mineralization process (e.g. entering a reactor) throughout the reporting period, in tCO2eq. It may be calculated using Eq. 20, or provided via other operations records.
(Eq. 11) ECO2 transport leakage=PurchasedCO2×Rleakage
Where,
ECO2 transport leakage was described in Eq. 9.
PurchasedCO2 was described in Eq. 10.
Rleakage represents the default leakage rate of the given transport mode (e.g. truck, pipeline...), for all transport modes used in project operations, in tCO2 lost/tCO2, or as a fraction.
(Eq. 12) ECO2 transport leakage=TCO2×Rleakage, T
Where,
ECO2 transport leakage was described in Eq. 9.
TCO2 represents the truck or ship transport segment considered, in tCO2*km.
Rleakage represents the default leakage rate of the given transport mode (e.g. truck, pipeline...), in tCO2 lost/tCO2*km.
Project feedstock provisioning
This life cycle stage shall include the production, processing, and transport of alkaline feedstock to be carbonated.
Requirements for modeling induced emissions from feedstock production are presented in Table 2.
Table 2 The approach for modeling GHG emissions from various types of feedstock are presented here.
Waste, no value
Recycled concrete aggregate
Feedstock enters the project system boundary with no emissions. The system boundary starts with the transport step where feedstock is diverted from its BAU use and sent to the project site, or the first non-BAU treatment step, whichever comes first.
Produced for the sole purpose of mineralization
Olivine
All feedstock production/mining/sourcing emissions shall be counted towards project induced emissions.
Valuable product, but not produced for the purpose of mineralization
Ordinary Portland cement (OPC) for carbonation curing
Production emissions are excluded, because they would have happened anyway/would be the same in the baseline scenario. The system boundary shall only include any processing steps specifically to prepare the feedstock for mineralization.
Valuable co-product
Steel slag
A share of the production emissions shall be allocated to the co-product, preferably based on economic allocation
Examples of feedstock processing/preparation for mineralization that may be considered in this stage may include but are not limited to:
feedstock preparation/processing to increase mineral purity (e.g. magnetic separation of iron), to increase carbonation rates
feedstock preparation/processing to increase surface area (e.g. grinding), to increase carbonation rates
heating, drying, wetting, to obtain optimal feedstock moisture content and diffusivity
For calculations and emission factors, see the Processing and energy use module.
Transportation of alkaline feedstock shall include the delivery transport from the alkaline material production source to the carbonation site. For calculations and emission factors, see the Transportation module.
Calculations: Project feedstock provisioning
(Eq. 13) Efeedstock=Efeedstock production+Efeedstock processing+Efeedstock transport
Where
Efeedstock represents the total project emissions from the feedstock provisioning life cycle stage, in tCO2eq.
Efeedstock production represents the emissions from feedstock production, in tCO2eq. This may be zero if the feedstock is a waste, may share emissions allocated between a coproduct, or may fully assume emissions if it is produced for the purpose of mineralization.
Efeedstock processing represents the emissions from any additional energy or mineralization materials used in feedstock processing (e.g. griding, heating...), calculated using the Processing and energy use module, in tCO2eq.
Efeedstock transport represents the emissions from transporting feedstock from its production site to the mineralization site, calculated using the Transportation module, in tCO2eq.
Project mineralization process
This stage includes induced emissions from the mineralization process, including energy use, input and machinery use, and transport/delivery of the carbonated material; plus any CO2 leaked from the reactor. All induced emissions from the mineralization process shall be included and counted towards the project GHG quantification, because they are all by definition additional to baseline conditions and part of the mineralization project.
This shall include energy use (electricity, heat and fuel) for heating, maintaining temperature, and compression/maintaining pressure, to be measured directly for each reported period. These may be provided by, for example:
measurements for the whole site, and allocated to the project if needed (e.g. site-wide electricity bills), or
measurements for specific machinery used by the project (e.g. energy meters), or
calculated using machinery power requirements and operation hours.
Depending on the project-specific technology, this may also include but is not limited to:
additives to increase dissolution rates (where dissolution of metal ions is the precursor to mineralization )
water
For energy use calculations and emission factors, see the Processing and energy use module.
All significant embodied emissions from machinery and infrastructure directly related to the mineralization process shall be included. For infrastructure calculations and emission factors, see the Infrastructure and machinery module.
Transport of the final product shall be included for any transport beyond 50 km, which is assumed to be the standard transport distance for conventional concrete and aggregates.
This is included because it cannot necessarily be assumed that the project and baseline transport is the same. Indeed, concrete is a commodity with relatively localized markets, whereas the project's innovative product may have buyers that are outside the typical radius of basic concrete transport.
For calculations and emission factors, see the Transportation module.
Project Developers shall either provide the amount of CO2 leaked or vented from a mineralization reactor, or justify why this amount can be assumed to be negligible.
Proof of the amount of CO2 leaked may include but is not limited to:
sensor measurements (actual sensor readings, or the amount of the detection threshold if the measured amount is zero)
reactor design documents showing an allowable or target limit of CO2 leakage
any approach mentioned in Article 41-46 of the EU ETS monitoring and reporting
mass balance of CO2 combining gas inflow-outflow and solid sample measurements, described below.
Fugitive CO2 emissions may be considered negligible if:
it is 100% biogenic and/or atmospheric CO2, or
it came from a flue gas stream, where the unused flue gas is emitted anyway, or
reactor design documents show negligible (<0.5%) CO2 leakage, and Project Developers prove adherence to reactor maintenance and calibration
This may be measured as CO2 leaked per hour of operation, or per tonne of carbonated material produced. The allocation of carbon type (fossil/calcination vs biogenic/atmospheric) shall be determined by the process detailed in the Allocation of captured carbon section.
Calculations: Project mineralization process
(Eq.14) Emineralization=Emineralization energy+Emineralization infra+Etransport+ECO2 leak
Where
Ecarbonation represents the total project emissions from the onsite carbonation life cycle stage, in tCO2eq per reporting period.
Emineralization energy represents the emissions from energy or consumable inputs used in the mineralization process, calculated using the Processing and energy use module, in tCO2eq.
Emineralization infra represents the emissions from infrastructure or machinery used for mineralization (i.e. reactors), calculated using the Infrastructure and machinery module, in tCO2eq per reporting period.
Etransport represents the emissions from transporting the carbonated material from its production site to the user, calculated using the Transportation module, in tCO2eq per reporting period. It is only considered if the transport distance is greater than 50 km.
ECO2 leak represents the emissions from direct CO2 leakage from the reactor/mineralization site to the atmosphere, in tCO2eq per reporting period. Project Developers shall calculate this in external files, using their preferred measurement setup, and report the final value per reporting period in the MRV.
Project CO2 storage
Carbon storage shall be determined using project-specific measurements and CO2 mass balance calculations, using either:
Solid sample: Periodic measurements on a representative sample of solid carbonated material, measuring its carbon content compared to a baseline material, using TGA or dry combustion/TCA
Gas inflow-outflow: continuous measurements of CO2 gas inflow minus outflow.
Each method is described in detail below. Cross verification of carbon storage measurements with another method is encouraged but not required.
Solid sample
All solid sample carbon content measurement shall be conducted on:
A carbonated sample from the project, and
A non-carbonated control sample of the same material.
The difference in CO2 content between the two, measured using TGA or dry combustion/TCA, shall be used to quantify the amount of CO2 removed by the project activity.
To ensure consistency:
Project and control samples must be collected at the same time interval after exiting the reactor (e.g. 24 hours, 1 week, 1 month).
Both samples must be stored under identical conditions between mineralization and measurement to avoid variations due to natural ambient mineralization.
All measurements shall be performed on at least one representative sample at the following frequency:
For each mineralization batch (with batch validity limited to 1 year), or
At least once per quarter, or
Every 500 tonnes CO2 removed, whichever comes first.
Refer to the Sampling and measurements section for detailed procedures on sampling approach, frequency, and traceability.
Calculations: Project CO2 storage, solid-sample
(Eq. 15) Sproject=ΔCO2eq∗AP, material
Where,
Sproject represents total carbon storage from the project in the reporting period, in tCO2eq.
ΔCO2eq represents the increase in CO2 storage in the carbonated material vs the baseline material, as an absolute increase of tCO2eq/t carbonated material. Calculated in Eq. 16.
AP, material represents the amount of carbonated material produced by the project in the reporting period, in tonnes of dry material.
(Eq. 16) ΔCO2eq=CO2eqproject−CO2eqcontrol
Where,
ΔCO2eq was described in Eq. 15.
CO2eqproject represents the concentration of CO2 equivalent in the carbonated project material, derived from measured carbonate content using an approved solid sample measurement (TGA or dry combustion), in tCO2eq/t of dry material. It is calculated in equations below for each measurement method.
CO2eqcontrol represents the concentration of CO2 equivalent in the non-carbonated control material, derived from measured carbonate content using the same measurement approach as for CO2eqproject . It is calculated in equations below for each measurement method.
Project Developers shall use either Eq. 17 or Eq. 18 to measure project and control CO2eq.
(Eq. 17) CO2eqproject, TGA=%CO2loss÷100
Where,
CO2eqproject, TGA represents the concentration of CO2eq in the material, tCO2eq/t of dry material, derived from measured carbonate content using TGA. The same equation shall be used for CO2eqcontrol.
%CO2loss represents the mass loss percentage of CO2, directly measured using TGA at 600–800 °C, in % mass loss or tCO2 lost/100 t dry material. Divided by 100 to convert to t/t.
(Eq. 18) CO2eqproject, dry combustion=%Cmass÷100×C to CO2
Where,
CO2eqproject, dry combustion represents the concentration of CO2eq in the material, tCO2eq/t of dry material, derived from measured carbonate content using dry combustion. The same equation shall be used for CO2eqcontrol.
%Cmass represents the measured inorganic or total carbon content of the material, in % mass of carbon or t C/100 t dry material. Divided by 100 to convert to t/t.
C to CO2 represents the molecular weight conversion factor between carbon and CO2, and equals 3.67.
Gas inflow outflow
Gas inflow-outflow measurements shall be taken continuously (at least 1x per minute) and summarized and reported daily.
Gas measurements shall use a calibrated flow metering with ±1.0% accuracy or better. Project Developers shall provide equipment calibration certificates and QA/QC procedures.
Any projects using:
Technology type: carbonated solid materials to add to e.g. concrete or asphalt, and
Measurement type: gas inflow-outflow,
shall also account for unreacted CO2 trapped in pore space of the carbonated material. This shall be calculated using conversions and subtracted from carbon storage measurements, according to Eq. 22.
Calculations: Project CO2 storage, gas inflow-outflow
(Eq. 19) Sproject=∑(InflowCO2−OutflowCO2−PoreCO2)
Where,
Sproject represents total carbon storage from the project, summed over the reporting period, in tCO2eq.
InflowCO2 represents the daily recorded mass of gaseous CO2 entering the carbonation process (e.g. entering a reactor), in tCO2eq, calculated in Eq. 20.
OutflowCO2 represents the daily recorded mass of gaseous CO2 exiting the carbonation process (e.g. exiting a reactor), in tCO2eq, calculated in Eq. 20.
PoreCO2 represents the unreacted CO2 stuck in pore space of the carbonated material, in tCO2eq, calculated in Eq. 21. It shall only be included for projects that carbonate solid materials (e.g. carbonating SCMs to add to concrete).
(Eq. 20) FlowCO2, i=VCO2, i∗CCO2, i
Where,
FlowCO2 i represents the flow of CO2 for i types of CO2, either inflow or outflow from the carbonation process, in tCO2eq/day.
VCO2, i represents the volume of CO2 inflow or outflow of the carbonation process, at standard temperature and pressure, in m3 of gas/day.
CCO2, i represents the weighted average daily concentration of CO2 inflow or outflow of the carbonation process, at standard temperature and pressure, in tCO2/m3 of gas.
(Eq. 21) PoreCO2=RTp×ϵ×yCO2×ρbulkMCO2
PoreCO2 represents CO2 trapped in pore space in the carbonated material, in tCO2eq/t carbonated material. This term is only required for projects carbonating solid materials, to add to e.g. concrete or asphalt.
RTp represents the molar concentration of an ideal gas (in this case, CO2), in mol/m3. Under standard conditions, the terms would be total gas pressure (p=101325 Pa ), temperature ( T=298 K), and the ideal gas constant ( R=8.3145J/(mol∗K)), for a total term value of 40.89 mol/m3.
ϵ represents the gas void fraction of the material (i.e. fraction of volume per m3 that is pore space), unitless. This value may be measured, or estimated using secondary literature for well-defined, common, homogeneous alkaline feedstocks.
yCO2 represents the molar fraction of CO2 in the pore gas, measured via gas analysis or conservatively assumed, unitless. It can conservatively be assumed to equal 1 (100% CO2 atmosphere).
MCO2 represents the molar mass of CO2, which equals 0.000044 t/mol.
hobulk represents the bulk density of the dry carbonated material, measured or estimated using secondary sources, in kg/m3.
Data sources
The required primary data for GHG quantification from all projects, regardless of measurement approach, are presented in Table 3. Required primary data for projects using solid-sample carbon storage measurements are in Table 4, and for projects using gaseous inflow-outflow are in Table 5. These data shall be provided for each reporting period, unless specified otherwise, and made publicly available.
Table 3 Summary of primary data needed from all projects and their source. Asterisks (*) indicate which data are only required for initial project certification and validation, and do not need to be monitored and updated during verification. Two asterisks (**) indicate which data are only necessary if the project is eligible for avoidance credits from reduced cement use.
Amount of CO2 leaving CO2 capture facility
t CO2 per reporting period
Operations records, sales contracts, invoices
Repartition of CO2 types purchased, entering mineralization facility
fraction
Operations records, sales contracts, invoices
Transport distance or amount of fuel, and transport mode, for CO2 delivery
tonne*km, or kg fuel, or L fuel
Operations records
Amount and type of alkaline feedstock used
tonne/reporting period
Operations records
Amount and type of infrastructure/machinery used for CO2 capture*
kg, tonne, or m3; and material type
Technical design documents
Amount and type of infrastructure/machinery used for mineralization*
kg, tonne, or m3; and material type
Technical design documents
Transport distance or amount of fuel, and transport mode, for alkaline feedstock delivery
tonne*km, or kg fuel, or L fuel
Operations records
Baseline removal calculations from alkaline feedstock mineralization
kgCO2eq/tonne feedstock
Models, calculations
Baseline and project concrete use phase carbonation calculations
kgCO2eq/tonne concrete
Models, calculations
Amount cement needed in project scenario**
kg cement used/reporting period
Operations records
Amount cement needed in baseline scenario**
kg cement equivalent calculated/ reporting period
Cement mix designs, statements from clients, mandatory concrete mixes
Cement mix design and emission factor for avoided cement**
kgCO2eq/tonne cement
Project-specific sources (e.g. EPDs), low-carbon cement thresholds (e.g. provided by the Global Cement and Concrete Association Low Carbon Rating), or Ecoinvent
Energy and/or material use from CO2 capture
kg, liter, kWh, MWh, GWh, m3; and material type
Operations records
Energy and/or material use from CO2 purification
kg, liter, kWh, MWh, GWh, m3; and material type
Operations records
Energy and/or material use from alkaline feedstock processing
kg, liter, kWh, MWh, GWh, m3; and material type
Operations records
Energy and/or material use from mineralization
kg, liter, kWh, MWh, GWh, m3; and material type
Operations records
Transport distance or amount of fuel, and transport mode, for carbonated material delivery (if distance >50 km)
tonne*km, or kg fuel, or L fuel
Operations records
Amount of carbonated material produced
tonne
Operations records
Table 4 Summary of primary data needed from projects using solid-sample CO2 storage measurements, and their source. Project Developers shall provide only one of the two data sources listed.
TGA: Carbon storage in project and control materials
mass loss percentage of CO2
Laboratory measurements
Dry combustion: Carbon storage in project and control materials
% mass of carbon or t C/100 t dry material
Laboratory measurements
Table 5 Summary of primary data needed from projects using gas inflow-outflow CO2 storage measurements, and their source.
Volumetric flow of CO2 inflow and outflow
m3 of gas/day
Primary measurements, sensors
Concentration of CO2 inflow and outflow
t CO2/m3 gas
Primary measurements, sensors
ϵ gas void fraction of the material (if carbonating solid materials)
fraction of volume per m3
measured or estimated using secondary sources
yCO2 molar fraction of CO2 in the pore gas (if carbonating solid materials)
unitless
gas analysis or conservatively assumed to equal 1
hobulk bulk density of the dry carbonated material (if carbonating solid materials)
kg/m3
measured or estimated using secondary sources
The ecoinvent database version 3.11 (hereafter referred to as ecoinvent) shall be the main source of emission factors unless otherwise specified. Ecoinvent is preferred because it is traceable, reliable, and well-recognized. The ecoinvent processes selected are detailed in Appendix 1.
Uncertainty assessment
See general instructions for uncertainty assessment in the Rainbow Standard Rules. The outcome of the assessment shall be used to determine the percent of RCCs to eliminate with the discount factor.
The following assumptions have low uncertainty:
Baseline delivery of concrete or aggregates is 50 km.
Directly carbonated cement will have no CO2 trapped in pore space.
The following assumptions have moderate uncertainty:
Future uses or end-of-life treatment of the carbonated material will not lead to reversals.
All carbonated material from the same mineralization batch has similar characteristics.
The baseline scenario selection at the methodology level has low uncertainty, because it requires a project-specific assessment of the specific amount and type. The specific circumstances, amount and type of baseline material must be proven by the Project Developer, and their uncertainty shall be assessed at the project level. There is low uncertainty that the baseline scenario includes baseline removals and cement.
The equations have low uncertainty, because they consist of straightforward conversions. No models are used in this methodology. Secondary data include default baseline mineralization rates for a selection of alkaline feedstocks, which comes with low uncertainty due to its very small contribution and the low sensitivity of final results to changes in this value.
The uncertainty at the module level is estimated to be low. This translates to an expected discount factor of at least 3% for projects using this module.
Last updated


